Re: Outside plant - prewire customer demarc preference
From: Justin Streiner <streinerj () gmail com>
Date: Fri, 8 Dec 2023 23:17:10 -0500
We just built a new house in 2021. The builder ran 2" schedule 40 from the side of the house out to the distribution point in front of my neighbor's house. I didn't specify 2" - that's what the builder ran. A portion of that run must have existed before construction because no one had to tear up my neighbor's yard to get to the distro box. Once I convinced Verizon that Fios was indeed available in this neighborhood (separate matter entirely), it was an easy matter for the tech to pull the drop cable through the empty conduit, drill a hole a few feet above the foundation and land the cable in the basement. I didn't run any surface tube or conduit in the basement, but there was enough room for the install tech to run the cable without too much of a fight. Thank you jms On Fri, Dec 8, 2023, 2:06 PM Eric Kuhnke <eric.kuhnke () gmail com> wrote:
If anyone assumes that residential real estate general contractors and low voltage/wiring subcontractors know or care about wifi signal or not putting RF units inside metal boxes - that would be a bad assumption to make. On Thu, Dec 7, 2023 at 10:18 PM Jay Hennigan <jay () west net> wrote:On 12/6/23 23:22, Eric Kuhnke wrote:I think an important point for pre-wire and residential real estate developers to consider is also the conflicting needs of keeping things "neat and tidy" and last mile CPE location vs wifi coverage.If you assume that the appropriate place for a wifi access point is colocated with the NID/ONT/CPE, you're doing it wrong. -- Jay Hennigan - jay () west net Network Engineering - CCIE #7880 503 897-8550 - WB6RDV
Current thread:
- Re: Outside plant - prewire customer demarc preference, (continued)
- Re: Outside plant - prewire customer demarc preference Jay Hennigan (Dec 02)
- Re: Outside plant - prewire customer demarc preference Brandon Martin (Dec 02)
- Re: Outside plant - prewire customer demarc preference Jay Hennigan (Dec 02)
- Re: Outside plant - prewire customer demarc preference Brandon Martin (Dec 02)
- Re: Outside plant - prewire customer demarc preference Sean Donelan (Dec 05)
- Re: Outside plant - prewire customer demarc preference Martin Hannigan (Dec 05)
- Re: Outside plant - prewire customer demarc preference Sean Donelan (Dec 05)
- Re: Outside plant - prewire customer demarc preference Gary Buhrmaster (Dec 06)
- Re: Outside plant - prewire customer demarc preference Eric Kuhnke (Dec 06)
- Re: Outside plant - prewire customer demarc preference Jay Hennigan (Dec 07)
- Re: Outside plant - prewire customer demarc preference Eric Kuhnke (Dec 08)
- Re: Outside plant - prewire customer demarc preference Justin Streiner (Dec 08)
- Re: Outside plant - prewire customer demarc preference Martin Hannigan (Dec 05)
- Re: Outside plant - prewire customer demarc preference Sean Donelan (Dec 07)