----- Original Message -----
From: "Michael DeMan" <nanog () deman com>

It is my understanding also that most commercial grade gensets have
built into the ATS logic that when utility power comesback online,
that the transfer back to utility power is coordinated with the ATS
driving the generator until both frequency and phases are within a
user specified range?

I don't believe that's actually true, Mike.  In a *load transfer* 
configuration, it's really not all that critical if the power presented 
to the load skips phase a touch on the transfer; there's a 50-500ms gap
in the power anyway, since such transfer switches are required by the
NEC to be non-shorting, so they don't electrocute power workers.

Cheers,
-- jra
-- 
Jay R. Ashworth                  Baylink                       jra () baylink com
Designer                     The Things I Think                       RFC 2100
Ashworth & Associates     http://baylink.pitas.com         2000 Land Rover DII
St Petersburg FL USA      http://photo.imageinc.us             +1 727 647 1274


Current thread: