On 4/30/2018 9:46 AM, Stephen Satchell wrote:
I've worked with APC, Synaccess, and a couple other brands of power controllers. One constant: the IP stack implementations tend to be a bit fragile. This is not restricted to power controllers; I have a GPS NTP appliance that is affected by the same sorts of things.I'll stick with APC and Synaccess, because I currently work with those. You want to avoid presenting these conditions to the embedded stack:1. ARP storms 2. Lots of layer 2 and layer 3 broadcast traffic 3. Probes for ports not implemented in the stack 4. Too much traffic (SNMP in particular)I like keeping all such devices on a single management VLAN dedicated to embedded-stack devices. The Ethernet hardware tends to be competent at filtering packets not intended for the device, so you don't have to go overboard with VLANs. It's the software behind the hardware that is easy to overwhelm if you throw too many packets at it.(But you knew this already)
In particular, if at all possible, do not use the AP9606 era cards with the APCs. They are 10BaseT and take fragile to a whole new level. I usually have to manually force the port to 10 on the switch or put it on a cheap dumb older switch.
The 961X series is 100BaseT and somewhat less temperamental. -- Brielle Bruns The Summit Open Source Development Group http://www.sosdg.org / http://www.ahbl.org
Current thread:
- Re: Remote power cycle recommendations, (continued)
- Re: Remote power cycle recommendations Tim Pozar (Apr 27)
- Re: Remote power cycle recommendations Keefe John (Apr 27)
- Re: Remote power cycle recommendations William Herrin (Apr 27)
- Re: Remote power cycle recommendations Brielle Bruns (Apr 27)
- Re: Remote power cycle recommendations Alan Buxey (Apr 28)
- Re: Remote power cycle recommendations Alain Hebert (Apr 30)
- Re: Remote power cycle recommendations Ben Cannon (Apr 28)
- Re: Remote power cycle recommendations Brielle Bruns (Apr 27)
- Re: Remote power cycle recommendations Tim Pozar (Apr 27)
- Re: Remote power cycle recommendations Roy (Apr 27)
- Re: Remote power cycle recommendations Jeroen Wunnink (Apr 30)
- Re: Remote power cycle recommendations Stephen Satchell (Apr 30)
- Re: Remote power cycle recommendations Brielle Bruns (Apr 30)
- Re: Remote power cycle recommendations William Herrin (Apr 30)
- Re: Remote power cycle recommendations Stephen Satchell (Apr 30)
- Re: Remote power cycle recommendations Stephen Satchell (Apr 30)
- Message not available
- Re: Remote power cycle recommendations Michel 'ic' Luczak (Apr 30)