Here is a little hint - most distributed applications in traditional jobsets, tend to work best when they are close together. Unless you can map those jobsets onto truly partitioned algorithms that work on local copy, this is a _non starter_.
Let's make it simple and say it in plain English. The users of services have made the decision that it is "good enough" to be a user of a service hosted in a data center that is remote from the client. Remote means in another building in the same city, or in another city. Now, given that context, many of these "good enough" applications will run just fine if the "data center" is no longer in one physical location, but distributed across many. Of course, as you point out, one should not be stupid when designing such distributed data centers or when setting up the applications in them. I would assume that every data center has local storage available using some protocol like iSCSI and probably over a separate network from the external client access. That right there solves most of your problems of traditional jobsets. And secondly, I am not suggesting that everybody should shut down big data centers or that every application should be hosted across several of these distributed data centers. There will always be some apps that need centralised scaling. But there are many others that can scale in a distributed manner, or at least use distributed mirrors in a failover scenario.
No matter how much optical technology you have, it will tend to be more expensive to run, have higher failure rates, and use more power, than simply running fiber or copper inside your datacenter. There is a reason most people, who are backed up by sober accountants, tend to cluster stuff under one roof.
Frankly I don't understand this kind of statement. It seems obvious to me that high-speed metro fibre exists and corporate IT people already have routers and switches and servers in the building, connected to the metro fiber. Also, the sober accountants do tend to agree with spending money on backup facilities to avoid the risk of single points of failure. Why should company A operate two data centers, and company B operate two data centers, when they could outsource it all to ISP X running one data center in each of the two locations (Company A and Company B). In addition, there is a trend to commoditize the whole data center. Amazon EC2 and S3 is not the only example of a company who does not offer any kind of colocation, but you can host your apps out of their data centers. I believe that this trend will pick up steam and that as the corporate market begins to accept running virtual servers on top of a commodity infrastructure, there is an opportunity for network providers to branch out and not only be specialists in the big consolidated data centers, but also in running many smaller data centers that are linked by fast metro fiber. --Michael Dillon
Current thread:
- RE: cooling door, (continued)
- RE: cooling door michael.dillon (Mar 29)
- Message not available
- Re: cooling door Robert Boyle (Mar 29)
- Re: cooling door Henry Yen (Mar 30)
- Re: cooling door Matthew Petach (Mar 30)
- Message not available
- Re: cooling door paul (Mar 30)
- Re: cooling door Deepak Jain (Mar 31)
- RE: cooling door david raistrick (Mar 29)
- latency (was: RE: cooling door) Mikael Abrahamsson (Mar 29)
- Re: cooling door vijay gill (Mar 31)
- RE: cooling door michael.dillon (Mar 31)
- Re: cooling door Christopher Morrow (Mar 31)
- Re: cooling door Patrick Giagnocavo (Mar 29)
- Re: cooling door John A. Kilpatrick (Mar 29)
- Re: cooling door Deepak Jain (Mar 31)
- RE: cooling door Buhrmaster, Gary (Mar 30)
- Re: cooling door Alexander Harrowell (Mar 30)