RE: San Francisco Power Outage
From: "Randy Epstein" <repstein () chello at>
Date: Wed, 25 Jul 2007 00:30:47 -0400
It appears that 365 is using the Hytec Continuous Power System [
<http://hitec.pageprocessor.nl/p3.php?RubriekID=2016> http://hitec.pageprocessor.nl/p3.php?RubriekID=2016], which is a motor, generator, flywheel, clutch, and Diesel engine all on the same shaft. They don't use batteries.
If the flywheels spent their energy before the generators came online, they
don't have the ability to start the generators up without utility power (unless they purchased the Dark Start option, which is simply extra batteries).
-brandon
They claim in the video tour that they do not have any battery systems on the site. They rely solely on the flywheels. Randy
Current thread:
- Re: San Francisco Power Outage, (continued)
- Re: San Francisco Power Outage John Kinsella (Jul 24)
- Re: San Francisco Power Outage Tuc at T-B-O-H.NET (Jul 24)
- Re: San Francisco Power Outage Justin M. Streiner (Jul 24)
- Re: San Francisco Power Outage Michael Painter (Jul 25)
- Re: San Francisco Power Outage Patrick Giagnocavo (Jul 24)
- Re: San Francisco Power Outage Jim Popovitch (Jul 24)
- RE: San Francisco Power Outage Alex Rubenstein (Jul 24)
- RE: San Francisco Power Outage Raymond L. Corbin (Jul 24)
- Re: San Francisco Power Outage Owen DeLong (Jul 24)
- Re: San Francisco Power Outage Brandon Galbraith (Jul 24)
- RE: San Francisco Power Outage Randy Epstein (Jul 25)
- RE: San Francisco Power Outage Brian Wallingford (Jul 25)
- Re: San Francisco Power Outage Jeff Aitken (Jul 25)
- Re: San Francisco Power Outage Paul Vixie (Jul 25)
- Re: San Francisco Power Outage Jason Matthews (Jul 24)
- Re: San Francisco Power Outage Michael Loftis (Jul 24)
- Re: San Francisco Power Outage Jonathan Lassoff (Jul 24)
- Re: San Francisco Power Outage Jason Matthews (Jul 25)
- Re: San Francisco Power Outage Paul Vixie (Jul 25)
- Re: San Francisco Power Outage Tuc at T-B-O-H.NET (Jul 24)