--- vijay gill <vgill () vijaygill com> wrote:

In all of the above cases, those were the large isps
that forced
development of the boxes. Most of the smaller
"cutting edge"
networks are still running 7513s.

Hmm - what I was getting at was that the big ISPs for
the most part still have a whole lot of 7513s running
around (figuratively), while if I were building a new
network from the ground up, I'd be unlikely to use
them.

GSR was invented because the 7513s were running out
of PPS.
CEF was designed to support offloading the RP.

2) they have an installed base of customers who
are
living with existing functionality - this goes
back to
reason 1 - unless there is money to be made,
nobody
wants to deploy anything.

3) It makes more sense to deploy a new box at the
edge, and eventually permit it to migrate to the
core
after it's been thoroughly proven - the IP model
has
features living on the edges of the network, while
capacity lives in the core.  If you have 3
high-cap
boxes in the core, it's probably easier to add a
fourth than it is to rip the three out and replace
them with two higher-cap boxes.

The core has expanded to the edge, not the other way
around.
The aggregate backplane bandwidth requirements tend
to
drive core box evolution first while the edge box
normally
has to deal with high touch features and port
multiplexing.
These of course are becoming more and more
specialized over
time.

I agree, from a capacity perspective: the GSR began
life as a core router because it supported big pipes. 
It's only recently that it's had anywhere near the
number of features which the 7500 has (and there are
still a whole lot of specialized features which it
doesn't have).  From a feature deployment approach,
new boxes come in at the edge (think of the deployment
of the 7500 itself: it was an IP front-end for ATM
networks)


4) existing management infrastructure permits the
management of existing boxes - it's easier to
deploy
an all-new network than it is to upgrade from one
technology/platform to another.

Only if you are willing to write off your entire
capital
investment. No one is willing to do that today.

That is EXACTLY my point: as new companies are
unwilling to write off an investment, they MUST keep
supporting the old stuff.  once they're supporting the
old stuff of vendor X, that provides an incentive to
get more new stuff from vendor X, if the management
platform is the same.

For instance, if I've got a Marconi ATM network, I'm
unlikely to buy new Cisco ATM gear, unless I'm either
building a parallel network, or am looking for an edge
front-end to offer new features.  
However, if I were building a new ATM network today, I
would do a bake-off between the vendors and see which
one met my needs best.

-David Barak
-Fully RFC 1925 Compliant-

=====
David Barak
-fully RFC 1925 compliant-

__________________________________
Do you Yahoo!?
Get better spam protection with Yahoo! Mail.
http://antispam.yahoo.com/tools


Current thread: