L-Root Maintenance 2010-01-27 1800 UTC - 2000 UTC
From: Mehmet Akcin <mehmet () icann org>
Date: Mon, 25 Jan 2010 01:56:56 -0800
Hi As part of staged, incremental deployment of DNSSEC in the root zone L-Root will begin serving a Deliberately Unvalidatable Root Zone (DURZ) after the completion of its scheduled maintenance at 2010-01-27 1800 UTC - 2000 UTC Please contact L-Root NOC via noc () dns icann org or T: +1.310.301.5817 if you have any questions. Please contact with rootsign () icann org if you have any questions regarding DNSSEC Deployment at root zone. Regards Joe Abley / Mehmet Akcin / Dave Knight ICANN DNS Ops / L-ROOT
Current thread:
- L-Root Maintenance 2010-01-27 1800 UTC - 2000 UTC Mehmet Akcin (Jan 25)
- <Possible follow-ups>
- Re: L-Root Maintenance 2010-01-27 1800 UTC - 2000 UTC Mehmet Akcin (Jan 27)
- Re: L-Root Maintenance 2010-01-27 1800 UTC - 2000 UTC Mehmet Akcin (Jan 27)