CAF nor RDOF required IPv6.  BEAD doesn't say anything about IPv6.  I
seriously doubt v6 gets included into the conversation because even NANOG
can't agree it is needed.  The bigger concern are the people that have no
connectivity at all (no 1 mbps, no 25/3, no 100/20, no gigabit, etc).

On Tue, May 24, 2022 at 9:41 AM j k <jsklein () gmail com> wrote:

With this funding, does the FCC require IPv6 and/or dual stack?  If not,
it could cause a new IPv6 digital divide.

Joe Klein

On Tue, May 24, 2022, 9:21 AM Max Tulyev <maxtul () netassist ua> wrote:

Do they help with a local government ("we do not need your cables, go
avway")?

23.05.22 21:56, Sean Donelan пише:

Money, money, money.


On Mon, 23 May 2022, Aaron Wendel wrote:

The Fiber Broadband Association estimates that the average US
household will need more than a gig within 5 years.  Why not just jump
it to a gig or more?


On 5/23/2022 1:40 PM, Sean Donelan wrote:


https://www.fcc.gov/document/fcc-proposes-higher-speed-goals-small-rural-broadband-providers-0

The Federal Communications Commission voted [May 19, 2022] to seek
comment on a proposal to provide additional universal service support
to certain rural carriers in exchange for increasing deployment to
more locations at higher speeds. The proposal would make changes to
the Alternative Connect America Cost Model (A-CAM) program, with the
goal of achieving widespread deployment of faster 100/20 Mbps
broadband service throughout the rural areas served by rural carriers
currently receiving A-CAM support.