nanog mailing list archives

Re: Any Verizon datacenter techs about?


From: William Herrin <bill () herrin us>
Date: Fri, 26 Jun 2015 11:34:55 -0400

On Fri, Jun 26, 2015 at 10:26 AM, Doug McIntyre <merlyn () geeks org> wrote:
Then it was announced ready to move in, and we asked the procedure to
get cross-connects from outside the facility in (really the whole
point of even getting colo there).

Oh no, you can't have a cross-connect.

Umm, the only reason we're doing this is to cross-connect to the colo.
The sales people knew this from the start, and was a key provision.
But the site manager was adamant, nothing comes in or out.

I'm told second hand that when MCI/worldcom (now Verizon Business)
controlled 8100 Boone Blvd (the early MAE-East) you had to buy a data
circuit from them to get between floors. Not a cable or a
cross-connect. A data circuit at the 0-mile tariffed price.

I know first hand that when I bought a Verizon Business data circuit
at a carrier-neutral colo and asked them to move the IP addresses from
my Verizon Business colo to the data circuit, they refused. It took me
longer but I canceled the colo anyway. And the circuit too. Jerks.

Regards,
Bill Herrin


-- 
William Herrin ................ herrin () dirtside com  bill () herrin us
Owner, Dirtside Systems ......... Web: <http://www.dirtside.com/>