Brandon Galbraith wrote:

My assumption is that it means "it isn't going to keep things cold, but it
will keep the air flowing to prevent a 'server sauna'".


On 7/25/06, Sam Stickland <sam_mailinglists () spacething org> wrote:

> -----Original Message-----
> From: owner-nanog () merit edu [mailto:owner-nanog () merit edu] On Behalf Of
> Sean Donelan
> Sent: 24 July 2006 13:27
> To: nanog () merit edu
> Subject: Re: Hot weather and power outages continue

> I've always been a fan of being able to force 100% economizer and
chiller
> loop bypass emergency operation; it won't keep you "cool" but will help
> keep your data center from turning into an Easy-Bake Oven(tm). But that
> failure operating mode is rarely part of the standard HVAC programming.

Sean,

Can you elaborate on what you mean by " force 100% economizer and chiller
loop bypass emergency operation"

Thanks,

Sam

When I was in charge of such things, there was a way to circulate evaporator tower water n the chilled water loop to remove some of the heat, if you had enough power to run the two pumps.


--
Requiescas in pace o email